Logo of the Electric Union.

This Saturday the service was affected by a deficit of generation capacity from 07:05 hours to 04:07 hours on Sunday (21:02 hours).

The maximum impact of the day was 406 MW, at 20:30 hours.

The availability of the SEN at 07:00 hours is 2100 MW and the demand 2110 MW with 30 MW affected, during daytime the service is estimated to be affected by a deficit of generation capacity in the order of 300 MW.

Unit 1 of the CTE Santa Cruz, unit 5 of the CTE Renté, unit 2 of the CTE Felton and Energas Boca de Jaruco are out of service due to breakdown. The CTE Guiteras unit, unit 5 of Nuevitas and unit 6 of the CTE Renté are under maintenance.

Limitations in thermal generation (441 MW) remain.

In distributed generation, 922 MW are unavailable due to breakdown and 164 MW are under maintenance.

For the peak, the entry of unit 2 of Robustiano León (Hydroelectric) with 14 MW, unit 1 of the CTE Santa Cruz with 60 MW and unit 3 of Energas Varadero, the recovery of 100 MW that are out of service due to lack of fuel and the entry of 2 engines in the Mobile Generation with 36 MW are estimated.

With this forecast, an availability of 2345 MW is estimated for the peak hour and a maximum demand of 2650 MW, for a deficit of 305 MW, so it is estimated an impact on the service of 375 MW at this time.

(Taken from UNE)