The Electric Union reports that yesterday the service was affected by a deficit in generation capacity from 17:26 p.m. to 23:01 p.m. (5:35 a.m.).

The maximum impact of the day was 251 MW, at 20:30 hours.

The availability of the SEN at 07:00 hours is 2290 MW and the demand 2150 MW, during daytime hours the service is not estimated to be affected due to a deficit of generation capacity.

Unit 2 of the CTE Santa Cruz and unit 2 of the CTE Felton are out of service due to breakdown. Out of service, due to the breakdown occurred in Puerto Escondido, which affects gas pumping, units 2, 3, 5 and 6 of Energas Jaruco. The unit of the CTE Guiteras, unit 5 of the CTE Nuevitas and unit 6 of the CTE Renté are under maintenance.

Limitations on thermal generation (352 MW) remain.

In distributed generation, 926 MW are unavailable due to breakdown and 172 MW are under maintenance.

For the peak, the entry of unit 2 of Robustiano León (Hydroelectric) with 14 MW and the entry of 2 motors in the Mobile Generation with 36 MW are estimated.

With this forecast, it is estimated for the peak hour an availability of 2340 MW and a maximum demand of 2700 MW, for a deficit of 360 MW, so it is estimated an affectation to the service of 430 MW at this time.