The Unión Eléctrica estimates for the night peak hours an availability of 2,657 MW and a maximum demand of 2,650 MW, for a reserve of 7 MW, therefore, if the forecast conditions are maintained, an affectation of 63 MW is forecast in

that schedule. 

At 7:00 a.m. this Friday, the availability of the National Electric System was 2,600 MW and the demand was 2,070 MW, with service throughout the system.

During the daytime there should not be any affectations to the service due to a deficit in generation capacity

.

Yesterday there were no affectations for that cause either.

Unit 3 of the CTE Santa Cruz and unit 2 of the CTE Felton are out of service due to breakdowns.

Unit 8 of the CTE Mariel, the CTE Guiteras unit, units 3 and 4 of the CTE Cienfuegos, unit 6 of the CTE Nuevitas and units 4 and 6 of the CTE Renté are under maintenance.

Limitations persist in thermal generation (263 MW).

Meanwhile, in distributed generation, 832 MW are unavailable due to failure and 109 MW are under maintenance.

For peak hours, the entry of unit 2 of CHE Robustiano León with 14 MW and the entry of an engine in the Mariel patana with 18 MW are estimated.