Secretary-General Zhan Rongfeng explained the reason for the rise of the administrative building of Yangmei District Office.

(Photo by reporter Xie Wuxiong)

[Reporter Xie Wuxiong/Taoyuan Report] Taoyuan Mayor Zhang Shanzheng established the "Taoyuan City Government Public Works Physical Examination Committee" at the end of last year, invited external experts and scholars to identify problems, and selected 3 major projects for medical examinations. Among them, the Yangmei District Office Administration Building will be completed in 2021. When a typhoon hit Lubi in August, the structure actually rose by 45 cm. It was finally determined that the drilling report was inaccurate and the groundwater level setting standard for flat land was applied to slope land.

Secretary-General Zhan Rongfeng said that the "Public Works Physical Examination Committee" also visited the site, discussed and communicated with the builder, design architect, and external structural audit unit on the cause of the accident and the construction process, and carefully inspected the facilities of the administrative building. Final verdict.

Please read on...

The administrative building of Yangmei District Office suffered continuous torrential rain from typhoon Lubi in the early August of the previous year, which caused the structure to rise 45 cm. Finally, the 15 parking spaces on the third basement floor were grouted to increase the load, and 79 ground anchors were added; in addition to an increase of 36.8 million yuan in funds In addition, 15 parking spaces have also been reduced.

It is reported that the project base of the administrative building of Yangmei District Office has a height difference of about 4 meters from north to south. The structure is tilted upwards, the part near Dacheng Road is raised by 45 centimeters, and the part near Dahua Street is 12 centimeters.