The Hsinchu City Government's Land Affairs Office stated that in order to relieve the rush of commuters from Zhubei to Zhuke Park, the self-administered rezoning of Guangpu Phase II will agree to give priority to the completion of the extension of Tzu Chi Road and Guanxin Road by the end of the year.

(provided by the city)

[Reporter Hong Meixiu/Hsinchu Report] In order to alleviate the influx of a large number of commuters from Jinzhuke Park, Zhubei City, Hsinchu County, the Land Affairs Office of the Hsinchu City Government coordinated the rezoning of Guangpu Phase II, which was initiated by the city. By the end of the year, the construction of the 165-meter-long section from Ciji Road to Gongdao 5th Road and the extended section of Guanxin Road will be completed, which will divert traffic from Zhubei to Zhuke Park and ease the long-term traffic congestion around Ciyun Road and the Science Park.

The Municipal Office of Land Affairs stated that because the right bank of Kezihu Creek on Lingong Road 5th Road within the self-administered city rezoning area of ​​Guangpu Phase II is under the jurisdiction of Hsinchu County, the extension of Guanxin Road is only planned to connect to the left bank of Kezihu Creek for flood control In the future, on the communication and integration platform of Hsinchu County and City, the road will be opened and extended eastward to Gongdao 5th Road in coordination with the Hsinchu County Government, hoping to divert the traffic flow from Jingguo Bridge in Zhubei to Zhuke, Zhushi.

Please read on...

According to the Lands Office, Guangpu Phase II self-administered city rezoning area covers an area of ​​97 hectares, with 22 hectares of park green space planned and 16 hectares of road land, including Cixiang Road and Ciji Road extending to Gongdao 5th Road and Guanxin Road. Extending to the Kezihu Creek flood control road, the widening of Puding Road and Guandong Road, and the plane road below the Taiwan Railway Neiwan Branch Line, etc., all of which are planned and constructed by the rezoning committee. It is expected that all development will be completed next year, and the general project development The amount reached more than 4 billion.

According to the Land Registry Office, the construction progress of Guangpu Phase II self-administered municipal land rezoning is currently about 40%. In order to relieve the traffic difficulties in the Guanpu area as soon as possible, the city government will coordinate with the rezoning committee and will ask the rezoning committee to give priority to Tzu Chi Road. For the planned road development project of Gongdao 5th Road, the city government will also coordinate with China Petroleum Corporation, Taipower, Water Supply and other pipeline institutions to enter the site and implement it simultaneously, and strive to complete it and open to traffic by the end of this year.

The traffic department of the municipal government pointed out that the traffic flow in the direction of Zhuke Park from Ciyun Road can reach 5,000 vehicles per hour during peak hours every day. Most of the vehicles entering Zhuke Park in Zhubei City are the main traffic nodes of Zhuke traffic congestion. The city government The traffic improvement team has listed the intersections of Gongdao 5th Road, Ciyun Road, Puding Road, and Jieshou Road in Guanpu area as the primary key improvement areas. Now the second phase of Guanpu self-run city rezoning will be under construction. If the construction company can give priority The opening of new roads from Ciji Road to Gongdaowu Road and the extension of Guanxin Road will ease the traffic flow from Zhubei to Zhuke Park.

The Hsinchu City Government's Land Affairs Office stated that in order to relieve the rush of commuters from Zhubei to Zhuke Park, the self-administered rezoning of Guangpu Phase II will agree to give priority to the completion of the extension of Tzu Chi Road and Guanxin Road by the end of the year.

(provided by the city)