This Monday the service was affected due to a capacity deficit from 10:11 a.m. to 12:32 p.m., with a maximum of 160 MW at 11:30 a.m., and during peak hours from 4:26 p.m. to 11:00 p.m.: 30 hours (07:04 hours).

The maximum impact at night was 541 MW at 7:00 p.m., coinciding with peak hour.

The availability of the SEN at 07:00 this Tuesday was 2,100 MW, and the demand was 2,060 MW, with the entire system in service.

The UNE reported on effects from 09:00 hours due to capacity deficit, with a maximum of 250 MW.

Unit 6 of the CTE Mariel, unit 3 of the CTE Santa Cruz, unit of the CTE Guiteras, unit 5 of the CTE Nuevitas, unit 2 of the CTE Felton and unit 5 of the CTE Rent.

Unit 4 of CTE Cienfuegos and units 4 and 6 of CTE Renté are under maintenance.

The limitations on thermal generation (237 MW) are maintained.

In distributed generation, 933 MW are not available due to failure, and 322 MW under maintenance.

For the peak hours of this Tuesday, the UNE foresees the entry of the Puerto Escondido unit, with 20 MW, and unit 5 of the CTE Rente, with 70 MW.

With this forecast, an availability of 2,277 MW and a maximum demand of 2,860 MW are estimated for the peak hour, for a deficit of 583 MW.

If the forecast conditions are maintained, an affectation of 653 MW is forecast at that time.