On the 27.5-kilometer section of Gongguan Township Chusulkeng Road in the east direction of Taiwan Highway 72, last year there was a landslide on the mountain wall and rocks that blocked the road.

After the Miaoli Public Works Section has been cleared, it is necessary to strengthen the protection of the slope surface.

(Provided by Miaoli Public Works Section)

[Reporter Peng Jianli/Miaoli Report] The Miaoli Public Works Section of the General Administration of Highways handles the 27.5-kilometer slope protection and bridge maintenance of the 72nd Route. If the timing of the traffic signal is not coordinated, the traffic flow is likely to be blocked; the Miaoli Public Works Department said that it has asked the manufacturer to adjust the seconds appropriately to facilitate the digestion of traffic flow.

27.5 kilometers east of Taiwan Highway 72, Chusongkeng Road Section, Gongguan Township, last year was blocked by earth and rocks on the slope of the mountain. After the Miaoli Works Section was cleared, the inspection of the slope surface needed to be strengthened. The bridges and roads also needed to be repaired due to the damage caused by the falling of huge rocks. .

Please read on...

The Miaoli Public Works Section will start a permanent restoration project after the Lunar New Year this year. From 9:00 am on March 1st to 4:00 pm on March 3rd, and from 9:00 am on March 6th to 4:00 pm on March 10th, the eastbound section from the Hakka Bridge to the Chusongkeng ramp will be closed For operation, passers-by going to the Dahu area turn left at the intersection of the Hakka Bridge and turn left on the plane road 119 Line A to connect to Taiwan Line 6, go to the exit ramp and connect to Taiwan Line 72 to the east.

However, many passers-by complained that the number of seconds to turn left at the intersection of the Hakka Bridge is too short, and the red light at the entrance of the ramp exiting the Sulfurkeng Road has to wait for a long time, which will easily cause traffic congestion. I hope that the construction unit can improve it.

In addition, the Miaoli Public Works Section considers that there are many tourists entering the Dahu Taian area during the holidays, and the construction is not closed during the holidays, which also caused local passers-by to complain about favoring one another and ridiculing "the most tourists".

In this regard, the Miaoli Public Works Department said that the manufacturer has asked the manufacturer to adjust the seconds appropriately for the two traffic signal lights at the entrance of the mine pit ramp and the eastbound turn left at the intersection of the Hakka Bridge to facilitate the digestion of traffic flow.

As the overall project is expected to last until August, this road section will still be closed for a long time, please bear with us.