The three-dimensional parking lot on Gong'an Road has progressed more than 40% and is expected to be completed in September.

(Provided by Yunlin County Government)

[Reporter Zhan Shihong/Yunlin Report] The three-dimensional parking lot on Gongan Road, Huwei Town, Yunlin County started construction in March last year. The current construction progress has exceeded 40%, which is a little faster than expected. It is expected to be completed in September this year. Zhang Lishan, Mayor of Yunlin County Today I went to survey the progress of the project, emphasizing that the county government team has been committed to improving the public project environment in recent years, simplifying relevant administrative procedures, and avoiding delays in appropriation of funds. It is hoped to attract high-quality manufacturers to invest. In the future, the new construction of the three-dimensional parking lot on Gongan Road will also participate in national competitions , hoping to create a high-quality new landmark.

Zhang Lishan said that the three-dimensional parking lot on Gong'an Road is expected to be completed in September this year. In addition to providing parking, the first and second floors can be used for commercial use. The county government has completed OT investment in January, and Sun Moon Pavilion Company has obtained the follow-up operation rights. The business unit An integration meeting has been actively held to clarify the follow-up use requirements early during the construction period, so as to facilitate early operation. Sun Moon Pavilion also promises to carefully select participating operators and create suitable operating characteristics.

Please read on...

Gongan Road three-dimensional parking lot is a three-dimensional parking lot with 6 floors above the ground and 1 floor underground. After completion, it can provide 296 parking spaces for cars and 30 parking spaces for motorcycles. The first and second floors are commercial spaces. It won the National Excellent Construction Award last year. Gold Medal in Planning and Design Category.

The total cost of the project is 633 million yuan, of which 120 million yuan is subsidized by the central government, and the rest is raised by the county itself.

The upper part of the parking lot is currently under construction, and the actual progress has reached 40%. The upper part of the project adopts a steel structure type, which needs to be hoisted, and the work area is limited. After the simulation and discussion of the moving line, the hoisting method will be carried out in partitions to avoid hoisting risks; Yunlin County Government He said that the safety and sanitation planning on the construction site is meticulous, which also drives good construction quality. He is expected to participate in the selection of this year's National Golden Safety Award and Gold Award.