The road surface of Dazhuang Road and Section 2 of Jiaxin East Road, Gangshan Highway 28, Kaohsiung, is about 3 kilometers away. Due to the frequent entry and exit of heavy vehicles, the road surface has serious potholes and depressions.

(Photo by reporter Su Funan)

[Reporter Su Funan/Kaohsiung Report] Kaohsiung Gangshan Highway 28 Dazhuang Road and Section 2 of Jiaxin East Road are about 3 kilometers away. Heavy vehicles frequently enter and leave the road surface, causing serious potholes and depressions. "Patches are like putting on dog skin plasters." Criticized by the public, it was ridiculed as "the worst road in Okayama". The General Administration of Highways and the Kaohsiung City Government allocated nearly 50 million yuan for improvement, which is expected to be completed next month.

Highway 28 starts from the Air Force Academy in the west and connects with Highway 29 to Agongdian Reservoir in the east. It is an important road connecting Yanchao and Tianliao in Gangshan, and it is also the only road to Gangshan Eye Park. Section 2 of Jiaxin East Road and Huagang Road It is also an important road connecting Gangshan to Alian and Tianliao. Because there are many screw factories nearby, heavy vehicles frequently enter and exit, resulting in serious potholes and depressions on the road surface. Driving is like riding a bouncing car, and frequent accidents have long been criticized by the public.

Please read on...

Highway 28 needs to improve the road surface from 5K+380 meters to 8K+500 meters, that is, from the archway of Guandi Palace in Dazhuangli to Section 2 of Jiaxin East Road and the intersection of Huagang Road, the length is more than 3 kilometers, and the total cost is nearly 50 million yuan. Huge, Legislator Qiu Zhiwei assisted the Kaohsiung City Government to seek financial subsidies from the General Administration of Highways. The General Administration of Highways approved the project funds before the Lunar New Year. Among them, the approved total project funds for the 28th section of the Highway were 48.488 million yuan, and the General Administration of Highways subsidized 39.76 million yuan. The government prepares a budget to make up for it.

The Gaoshi Maintenance and Works Office pointed out that after the roadbed survey of Highway 28, it was found that the foundation of the road base was weak and must be thoroughly improved. After the roadbed was excavated 50 cm of soil, low-strength concrete was poured in to improve the roadbed, and the upper layer was paved with wear-resistant improvement. Quality 3 type asphalt concrete 10 cm, completely improving road quality.

At present, the engineering personnel have completed the survey and boundary marking operations, and completed the trial planing at the starting point. The construction will start in succession in the near future, and the goal is to complete the improvement work on the whole line in March.

Dazhuang Road, Highway 28, "patches are like putting on dog skin plaster", has long been criticized by the public, and has been ridiculed as the worst road in Okayama.

(Photo by reporter Su Funan)

There are many screw factories near Gangshan Highway 28 and Section 2 of Jiaxin East Road, and heavy vehicles usually come in and out frequently.

(Photo by reporter Su Funan)