The article in the annual special publication of the Central City Government stated that "Taichung Dome will start construction by the end of 2022." City Councilor Yang Dianzhong criticized the expansion, and the bid has been rejected again.

(Photo by reporter Su Jinfeng)

[Reporter Su Jinfeng/Taichung Report] All district offices of Taichung City will print annual special publications by the end of 2022, covering major construction projects in the city and in various districts. Construction will start at the end of 2022", has the stadium started yet?

After checking, he found that the dome had lost bids before the Lunar New Year this year. Yang Dianzhong said that the municipal publicity materials had made false propaganda. It is more practical to reduce the construction period and reduce the waste of public funds.

Chen Datian, director of the Construction Bureau, said that the previous six tenders for the Taichung Arena were rejected because the number of bidders did not reach the statutory number. After consulting with the outstanding construction teams in the industry, they said that due to rising prices and a large number of public works, most of the competent construction companies were more Insufficient manpower, stretched, and because the Taichung Arena is a landmark building project of the city government, with a large scale and complex interface, manufacturers are relatively cautious in evaluating the content of bids and preparing bids. However, after the announcement of bidding, there are still calls from manufacturers asking about bidding It is obvious that the industry's outstanding construction teams and professional manufacturers from all walks of life are very interested in the Taichung Arena.

The city government is still actively rushing forward with the goal of successfully awarding contracts and starting construction in 2023.

Please read on...

Yang Dianzhong said that some people have reported to him that the Taichung City Government issued an annual special issue. The article said that the Taichung Arena will start construction by the end of 2022. Has it started now?

But the fact is that on January 17, the bid failed again.

Yang Dianzhong criticized that since the construction of Taichung Arena could not start at the end of last year, of course the completion date will be postponed later.

Will the construction period of the Marine Life Museum be extended?

Call on the city government to do things pragmatically and stop talking about the completion date of the wind.

In addition, Yang Dianzhong said that the annual special issue of the city government is the promotional materials purchased and printed by each district office at the end of last year. The content of the special issue has two parts, one is the municipal construction of Greater Taichung, and the other is the local construction of each district.

Yang Dianzhong said that the city government’s annual special publications are edited and printed by each district, so that some district offices make small purchases because the funds do not reach 100,000 yuan, and the price difference in the unit price of each propaganda product reaches 75%. 22,000 sheets are less, each priced at 4.45 yuan, and the unit price of 92,000 sheets in Xitun District is 2.8 yuan.

He requested that the printing of publicity materials can be coordinated and contracted to reduce the price difference, otherwise the unit price of the annual special issue in other administrative regions with fewer households may be higher.

The Civil Affairs Bureau stated that due to the differences in the population structure and cultural industries of the 29 districts of Taichung City, the special issue is compiled by the Civil Affairs Bureau in the municipal construction of Greater Taichung, and the local characteristics are integrated into the editorial content design and printing of the special issue by the district offices to suit the local people. needed.