The pressurization station of Sanchong No. 2 distribution pool held a ground-breaking ceremony yesterday. After completion, it will bring more guarantees for water supply in Sanchong and surrounding areas such as Luzhou, Xinzhuang, and Wugu.

(Photo by reporter Lin Xinhan)

It can greatly increase the water storage and regulation capacity, and the water supply of Sanchong, Luzhou, Xinzhuang and Wugu is more stable

[Reporter Lin Xinhan/New Taipei Report] The Taipei Waterworks Department spent more than 1.4 billion yuan to build Sanchong No. 2 distribution pool pressurization station, with a total capacity of about 2.5 billion yuan.

40,000 tons and is expected to be completed in July 2027. The North Water Department pointed out that after the completion of the pressurization station, it will increase the stability of water supply in Sanchong and surrounding Luzhou, Xinzhuang, Wugu and other areas; it will also provide shopping malls, Office rental space, active rezoning of commercial functions.

Please read on...

The North Water Department spent 1.4 billion to build and complete in 2027

Taipei Mayor Ke Wenzhe presided over the ground-breaking ceremony yesterday. Ke Wenzhe said that the North Water Station not only supplies water to Taipei City, but also includes the Xindian Ankeng area, Zhonghe, Yonghe, Xinzhuang, Wugu, Bali, Sanchong, Luzhou and other places in New Taipei City. The water supply range is divided into ten districts, and he requires at least two backup systems in each district to ensure stable and safe water supply.

After the Sanchong No. 2 water distribution tank pressurization station is completed, the water storage and regulation capacity can be greatly increased, and it will operate jointly with the existing Sanchong No. 1 water distribution tank pressurization station to establish a backup support system for the triple water supply zone and increase the maximum processing capacity.

According to the Beishui Department, the pressurization station of Sanchong No. 2 distribution tank is located at the intersection of the first section of Shuhong East Road and Chenggong Road. The base area is about 4,150 square meters and it is underground 2.

40,000-ton water distribution pool, two buildings on the ground, two-story reinforced concrete structure, the main building is a pressurized equipment room, with an area of ​​about 1,414 square meters, and the attached building is a shopping mall with a multi-purpose area of ​​about 1,105 square meters or Office space rental, total expenses 14.

2.9 billion yuan and is scheduled to be completed in July 2027.

Also provide shopping malls, office space for rent

The North Water Department added that in response to climate change, it will improve the risk of large-scale water supply to strengthen the system and stabilize the water supply. The Central Water Source Dispatch has supported Taiwan Water Supply Company, from 190,000 tons per day in 2005 to nearly 770,000 tons per day last year, and the proportion of water supply in New Taipei City has also increased from 37% to 52%. The amount of water in the vicinity of Xizhi ranges from one.

20,000 tons increased to 8.

650,000 tons.

The Taipei Water Works Department spent more than 1.4 billion yuan to build the pressurization station of Sanchong No. 2 distribution tank, which is expected to be completed in July 2027. The picture shows the schematic diagram of the completion.

(Provided by Taipei Water Works Office)