We commissioned the first stage of the interconnector to have gas and benefit from it.

We have left certain construction activities for the second and third stages.

We aim to finish them as well.

There is one road that was not completed, one fiber optic cable and some measures.

This was stated by the Acting Minister of Regional Development and Public Works, Ivan Shishkov

Ivan Shishkov was born on September 14, 1963 in Sofia.

He graduated with a master's degree in the program "More of the Day" on BNT.

"Until the inauguration of the official office, all sites of the interconnector had Act 14 - i.e.

rough construction.

At this moment, the site is still not 99% complete," he emphasized.

"My ambition is to finish everything that is not finished, to design everything that should have started, as quickly as possible," admitted Minister Shishkov.

The regional minister: I commissioned the design of the highway from Ruse to Makaza

“We have approved the detailed development plan for construction to begin.

The detour from Ruse to Byala was even declared a national site.

The tunnel under Shipka is part of the construction chaos we found.

It has no serious meaning, because the bypass of Gabrovo has two lanes and has already been done.

We will give a lot of money for a minimal effect", explained Ivan Shishkov

Ivan Shishkov was born on September 14, 1963 in Sofia.

He graduated with a master's degree in

"There is a very big delay on a number of projects," the regional minister admitted.

"The route to Slivnica from AM Europe was stopped.

The detailed development plan was not accepted and thus we lost 7 months.

In 4-5 months, construction will begin, but we will lose part of the European funding because the builder will not have time," he admitted.

"We have signed the assignment for the detailed layout plan for the National Children's Hospital.

Construction will begin when the detailed development plan comes into force and there is a project.

We have made a very precise plan.

The next government will be able to start construction," the regional minister announced.

On the subject of energy efficiency, Minister Shishkov stated: "The remediation program will begin within 10 days.

Until March, the program is 100% financed, after March - with 20% participation of the owners".