The basement foundation works of the Huwei Public Security Parking Lot were carried out, and the construction progress was ahead of schedule.

(Photo by reporter Zhan Shihong)

[Reporter Zhan Shihong/Yunlin Report] The Yunlin Huwei Public Security Stereoscopic Parking Lot, with a total construction cost of 633 million yuan, won the 2022 National Excellent Construction Award for Best Planning and Design Gold Award this year. After completion, it can effectively relieve the urban area of ​​Huwei. Due to the lack of parking spaces, the shopping malls on the 1st and 2nd floors can also increase employment opportunities and business opportunities. The current construction progress is ahead of schedule.

The Public Works Office of Yunlin County Government stated that the Public Security Parking Lot is located in the center of Huwei Town, adjacent to the commercial belt of Linsen Road. The design took "tree" as the overall concept, and proposed "urban green building = parking lot + shopping mall + vertical forest" as the main design concept. Taking the pedestrian square activity area and urban landscape texture into consideration, an urban forest with 6 floors above ground and 1 floor underground is built. After completion, it is expected to provide 296 car parking spaces and 30 locomotive parking spaces. Considering that it is located in the commercial area, parking lot 1. Commercial space is set up on the 2nd floor, which won the gold award in the best planning and design category of the 2022 National Excellent Construction Award this year.

Please read on...

Director of Public Works Wang Lingyao accompanied the county magistrate Zhang Lishan, Huwei Mayor Ding Xuezhong and several councillors to inspect the progress of the project today. Wang Lingyao said that since the construction site is located in the city center and is close to the county puppet theater, construction safety has become extremely important. When it is used as a retaining support, the county government requires that the impact of vibration must be avoided through monitoring operations.

The foundation excavation project and grounding work were completed in early September, and the steel reinforcement project for the underground structure is currently underway. As of now, the scheduled progress is 11.31%, and the actual progress is 11.72%, which is 0.41% ahead. , it is necessary to speed up the operation under the premise of no problem of quality.

The basement foundation works of the Huwei Public Security Parking Lot were carried out, and the construction progress was ahead of schedule.

(Photo by reporter Zhan Shihong)