The Hemus Freeway was "frozen" in early spring due to non-payment.

The last one was made by the previous office at the end of November 2021.

This was said by the Acting Minister of Regional Development and Public Works Arch.

Ivan Shishkov

Ivan Shishkov was born on September 14, 1963 in Sofia.

Completes a master's degree in after inspection of the first two of the remaining sections of the infrastructure object.

The inspection was also attended by Deputy Minister Zahari Hristov and the Chairman of the Management Board of the Road Infrastructure Agency, Ivo Ivanov, the press center of the Ministry of Infrastructure, Transport and Tourism reported. 

Minister Shishkov inspects the construction of AM "Hemus"

The inspection is being carried out in order to make the appropriate decision and to be able to build this part of the "Hemus" highway, which has building permits, in the shortest possible time, Shishkov also said.

We expected that section 1 - from Boaz to p.

v. "Dermantsi" is in a more advanced phase.

The construction of the second one, between the "Dermantsi" and "Kalenik" road junctions, is at a very early stage.

There is not much excavation work on it, construction equipment is piled up, but no workers.

The contractors of the different sections are different, although according to documents the builder is the state company "Automagistrali" EAD, the regional minister also said.

And he said he would ask the state-owned company for information about payments to construction companies. 

Regardless of whether they are in the budget of the Road Infrastructure Agency or not, an opportunity will be sought to pay the funds so that the construction process can continue, Ivan Shishkov committed

Ivan Shishkov was born on September 14, 1963 in Sofia.

He graduated with a master's degree in

And he added that he would request that the deadlines not be extended if possible.

Section 1 is well advanced in construction and if the critical points are cleared, we will be nearing construction completion.

The builder has to compensate for the delay.

It will be required to carry out certain construction activities until the winter period, because some of the major bridge facilities in it have advanced.

They must be completed so that they are not compromised if they remain unfinished for another winter, the minister informed. 

The construction of the first section should be completed by the middle of next year.

The commissioning of the first three sections - up to p.

c. "Kalenik", depends on the construction of the second one, which started at the latest.

Therefore, the work on it should not be delayed, he was categorical.

Ivan Shishkov

Ivan Shishkov was born on September 14, 1963 in Sofia.

He is completing a master's degree in pointed out that nothing has been done to legalize in favor of the state the illegal construction found by the previous office in sections 4 and 5, so that it does not have to be demolished and have to be done again.

It was of utmost importance to approve an amendment to the Zoning Act and to declare tolerable illegal construction that complies with the norms.

We had proposed a text to the management of the MRRD in the regular cabinet.

That didn't happen.

Therefore, at the moment I cannot comment that there is a mechanism to start construction in these two sections, said the regional minister. 

We will do our best not only to control the started construction of the large infrastructure objects, but to give an impetus to new ones, at least in terms of planning, so that we can have passable roads and not "plugs" on them, said arch.

Shishkov.

It is necessary to start impact design.

The north-south axis in Bulgaria is practically undeveloped, including in terms of design.

In the last 10 - 15 years, the construction of the infrastructure has been very late and is at an extremely slow pace.

Small sections were being built and used for political purposes, the minister said.

The infrastructure should not be for political purposes, but should be built for all citizens and be safer, arch.

Shishkov.

After inspecting the work in the "Vitinya" tunnel, the regional minister expressed his disappointment that the evacuation exits are being made without the necessary finishing works.

This can cause a serious delay.

Therefore, a conversation with the management of "Automagistrali" EAD is pending in order to establish the reasons for the delay and to speed up the process. 

An inspection of the construction of the "Struma" highway is also pending, announced Ivan Shishkov

Ivan Shishkov was born on September 14, 1963 in Sofia.

He graduated with a master's degree in

A serious problem there is the activated landslide before the railway viaduct and tunnel.

We will try to introduce a temporary organization of traffic if possible so that the section can be put into operation, he announced.

The Vidin - Botevgrad expressway will also be inspected.