The repair of 11 road sections with a total length of nearly 200 km in the districts of Varna, Burgas, Stara Zagora, Haskovo, Vidin and Smolyan will start this year, the press center of RIA announced.

The Road Infrastructure Agency announced the public procurements for selection of contractors for the construction and installation works / construction and installation works / for major repairs of the sections.

Among them are routes proposed by citizens for inclusion in the repair program of RIA for 2022, such as Dyulin Pass, which is the shortest connection between the municipalities of Varna and Burgas through the Balkan Mountains and is an alternative route to the first class road I-9 Varna - Burgas.

The repair of the sections Rosen - Veselie - Yasna Polyana and Marinka - Vizitsa in Burgas district will start, as well as on the road Rabrovo - Perilovtsi - Shishentsi in Vidin district, for which the citizens have also sent proposals.

RIA increased the requirements for the contractors of construction and construction supervision both during the repair works and in the warranty period after that.

The aim is to ensure quality execution of construction and installation works.

Minister Karadjov among the protesters: The money for the roads is a hostage of the election for head of the BNB

There is a new obligation for the construction supervisor to have an accredited construction laboratory, different from the one that the builder will use.

The aim is for the consultant to carry out mandatory own tests, trials and inspections during the implementation and acceptance of the construction activities.

There is also a twice longer warranty period for road works - 6 years, instead of the previous 3 years.

During the warranty period, in addition to the regular inspections of the contracting authority - Road Infrastructure Agency, there will also be mandatory inspections twice a year.

In case of establishing technical errors and discrepancies in the certificate for performed construction works, approved by the supervision and submitted for final approval and payment to the contracting authority, sanctions may be imposed on the construction supervision.

The construction supervision is additionally charged with coordinating and controlling the temporary organization of traffic in order to increase safety during construction.

The bids of the participants in the two announced public procurements will be accepted until May 12, 2022. One public procurement is for selection of a contractor for construction and installation works for major repairs of 123.5 km of roads with a total indicative value of BGN 135,889,600 excluding VAT.

It is divided into five separate positions:

• In separate position I is the main repair of 34.1 km of road III-906 (I-9 Staro Oryahovo - Obzor) - Gyulovtsa, including the route of the Dyulin Pass.

The section passes through the districts of Varna and Burgas.

Two facilities will be repaired in the section - a bridge over the river Dvoinitsa at the 13th km and a bridge over the river Byala at the 32nd km.

The estimated value is BGN 37,510,000 without VAT.

The term for the repair is 540 calendar days;

• In separate position II is the overhaul of 31,534 km of road III-906 Gyulovtsa - Kableshkovo - crossroads with road I-9 Sunny Beach - Bourgas, in Bourgas district.

In the section 4 bridges will be renovated - over the Byala River at the 37th km, over the irrigation canal at the 40th km, over the overflow of the Poroy Dam at the 42nd km and over the Aheloy River at the 45th km, as well as large facility at the 55th km.

The indicative value is BGN 34,687,400 without VAT.

The term for the repair is 540 calendar days;

• In the separate position III is the main repair of 24.6 km of road III-907 (road I-9 Marinka - Zvezdets) - Vizitsa - (road II-99 Tsarevo - Malko Tarnovo). is the main road connection of the settlements in the municipality of Malko Tarnovo with the Black Sea coast and Turkey.The estimated value of the contract is BGN 27,060,000 without VAT.The term for the repair is 450 calendar days;

• In separate position IV is the overhaul of 21,441 km of road III-992 (Burgas - Sozopol) - Yasna Polyana - Primorsko in the section of the junction with the road Burgas - Sozopol, through Rosen and Veselie to Yasna Polyana.

The route is an alternative route of the second class road II-99 Burgas - Primorsko.

There are two large facilities in the section, which will be replaced with new ones due to damage to the foundations and foundations: a bridge over the Rosenska River at 7 km and a bridge at 9 km.

The indicative value is BGN 23,585,100 without VAT.

The term for the repair is 450 calendar days;

• In separate position V is the overhaul of 11,861 km of road III-9009 Novo Panicharevo - Yasna Polyana.

The section is part of the route Burgas (Kraimorie) - Marinka-Novo Panicharevo-Yasna Polyana - Primorsko, which duplicates road II-99 in the section to Primorsko and provides access to the Southern Black Sea coast.

Two bridges will be repaired in the section - over the Ropotamo River and a facility at the 6th km.

The estimated value is BGN 13,047,100 without VAT.

The term for the repair is 360 calendar days.

The second public procurement is for major repairs of 76.2 km of national roads.

The total indicative value is BGN 83,428,400 without VAT.

The tender procedure is in 6 separate positions:

• In separate position I is the main repair of 7,840 km of road III-9061 (Orizare - Kableshkovo) - Tankovo ​​- Sunny Beach in the section of the junction with the road Orizare - Kableshkovo, through the village of Tankovo ​​to Sunny Beach.

The section provides a transport connection for travelers from the interior of the country to the Bulgarian Black Sea coast and is used as a bypass route on the road I-9 Varna - Bourgas when stopping freight traffic during the summer season.

Two bridge facilities will be repaired in the section - at the 3rd and at the 7th km.

The estimated value is BGN 8,624,000 without VAT.

The term for the repair is 300 calendar days;

• In separate position II is the overhaul of 6,491 km of road III-6009 Kableshkovo - Aheloy, in Burgas district.

The route provides a transport connection from p.

Bulgarovo newspaper on the Trakia Motorway to the Southern Black Sea Coast and is used as a direct connection with Sunny Beach.

The indicative value is BGN 7,140,100 without VAT.

The term for the repair is 300 calendar days;

• In separate position III is the overhaul of 16,129 km, and road connections with a total length of 0.320 km, from road III-7907 Debelt - Bratovo.

The section connects the municipalities of Burgas, Kameno and Sredets and is the main route for trucks traveling to the refinery.

4 facilities will be renovated in the section: overpass over the railway line, bridge over the Rusokastrenska River, arch bridge over the Maladzhiysko Dere River and bridge over the Chakarliyka River.

The estimated value is BGN 17,741,900 without VAT.

The term for the repair is 360 calendar days;

MP from the RIA money: The process is not sabotaged, we wanted to have a clear mechanism

• In separate position IV is the overhaul of 11,841 km of road III-121 Rabrovo - Perilovets - Shishentsi, which is the shortest road connection of the settlements in the municipalities of Vidin and Kula in Vidin district.

It is planned to build a new bridge on the site of the existing one over the Rabrovska River at the 23rd km.

The indicative value is BGN 13,025,100 without VAT.

The term for the repair is 360 calendar days;

• In separate position V is the main repair of 11,612 km of road III-807 Varbitsa - Skobelevo, which connects the districts of Stara Zagora and Haskovo.

The section will repair the steel bridge over the Maritsa River at the 7th km, which was built in 1932 and has not been overhauled since.

Due to its deteriorating condition, it has been closed to traffic since 2010. The bridge over the Byala River at the 6th km will also be renovated.

The estimated value is BGN 12,773,200 without VAT.

The term for the repair is 360 calendar days;

• In separate position VI is the overhaul of 21,931 km of road III-868 Rudozem - Smolyan.

The section serves the settlements in the municipalities of Rudozem and Smolyan and is an alternative route for access to the future border checkpoint "Rudozem - Xanthi".

The route provides a connection with the monument on Srednogorets peak, known as the Rhodope Shipka, built in honor of the liberation of the Rhodopes in 1912. The estimated value for the supervision of the site is BGN 24,124,100 without VAT.

The term for the repair is 450 calendar days.

For the repair of the 11 third-class routes at the end of March this year.

the tender procedures for selection of contractors for construction supervision were announced.